Our plan was to establish an interdisciplinary care unit to house the departments of pediatric oncology, pediatric orthopedics including a clubfoot clinic, physiotherapy and orthopedic technology, as well as social pediatrics. Following discussions with the Eritrean Ministry of Health, we were offered the use of “WARD F,” a then-unused, somewhat dilapidated and cluttered side wing of the children’s hospital at Orotta Hospital in Eritrea’s capital, Asmara.
Before we could begin the actual construction and renovation work, however, we had to wait for the renovation of the pediatric intensive care unit PICU, which was temporarily housed in WARD F until April 2023.
read more
Since then, mixed construction teams have been deployed several times a year under the direction of our construction engineer, Norbert Kessler. Cooperation with the medical project leaders is of great importance, as they provide the specifications for the design and use of the rooms. The pediatric oncology ward in particular has special requirements regarding hygiene and function. All work is carried out together with the Eritrean helpers whenever possible.
First, all rooms were cleared so that compressed air and oxygen could be installed. Old water pipes were removed and new installations of water (service and drinking water) and wastewater were carried out, all supply lines were installed, and sinks were mounted. In the area of power supply, all switches, cables, distributors, sockets, and connections were installed, and the pediatric oncology area was equipped with supply rails. New flooring was laid, and defective windows and window panes were replaced. The orthopedic workshop received workbenches and washing tables. Additional nurses’ and doctors’ rooms were created and furnished.
Before the ward is completed in spring 2025, the suspended ceilings in the corridors still need to be installed and the ceiling lighting fitted. Hot water boilers, faucets, and wastewater pipes will still be installed. Walls, door frames, and interior doors will be painted by the Eritrean staff. The windows will be fitted with either curtains or opaque film. Since the exterior doors are in poor condition, we will probably have to replace them as well. Wherever possible, materials available in Eritrea are sourced and procured locally.